Bathroom Renovation Cost Estimator: Build a Real 2026 Budget
Estimating a bathroom renovation is really just eleven line items and one honest contingency. Here's how to build the number yourself.
There's a difference between a price and an estimate. A price is what one contractor will do it for. An estimate is what the work should cost anywhere — and once you can build one, no bid can surprise you.
The Eleven Line Items in Every Bathroom Renovation
- Demolition and disposal: $600–$1,800
- Rough plumbing (no relocation): $900–$2,200 · with relocation: $2,500–$6,000
- Electrical, GFCI and exhaust fan: $650–$2,000
- Framing and blocking: $300–$1,200
- Waterproofing and backer board: $500–$1,600
- Tile material: $3–$18 per sq ft · tile labor: $9–$22 per sq ft
- Tub or shower base: $450–$3,500
- Shower glass: $700–$3,200
- Vanity, top and faucet: $800–$4,500
- Paint, trim and accessories: $400–$1,200
- Permits and general conditions: $400–$1,500
A Worked Example: 45 Sq Ft Hall Bath
Keep the layout, replace everything, mid-range finishes. Demo $1,100 · plumbing $1,600 · electrical $950 · waterproofing $900 · tile 110 sq ft at $6 material and $14 labor = $2,200 · shower base and valve $1,300 · glass door $1,500 · vanity package $1,900 · paint and trim $700 · permits $600. Subtotal $12,750. Add 12% contingency: $14,280.
Run the same math for your bathroom automatically.
Open the Bathroom Renovation Budget CalculatorWhere Estimates Go Wrong
- Forgetting tile labor is usually double tile material.
- Pricing a vanity but not the top, faucet, drain and install.
- Ignoring the exhaust fan and code-required makeup air.
- Assuming the shower glass is included — it's almost always a separate vendor.
- No contingency. This is the single most common budget failure.
Trimming the Estimate Without Cheapening It
Tile the wet walls to ceiling and paint the rest. Choose a stock vanity in a standard width. Keep to 12×24 porcelain rather than mosaic fields. Reuse the existing toilet location. You can save $3,000–$5,000 on a mid-range bath with those four calls alone, and no guest will ever notice.
FAQ
How do I estimate a bathroom renovation cost?
Total the eleven standard line items — demo, plumbing, electrical, framing, waterproofing, tile, shower or tub, glass, vanity, paint and permits — then add a 10–15% contingency. That total should track within 15% of real bids in your market.
What percent of a bathroom renovation is labor?
Roughly 55–65% in 2026. In high-cost metros like San Francisco and New York it can reach 70%, which is why identical material lists produce wildly different totals across the country.
How much contingency should I hold?
Ten percent for a home built after 2000, and fifteen to twenty percent for anything pre-1980 where plumbing, wiring and subfloor surprises are common.